  • Berri & Marjan Project: Multiple Jacket Lifts
    October 2017

    BACKGROUND

    In October 2017 KTL Offshore was awarded the contract to design, manufacture and test 22 heavy lift slings for an offshore contractor under a long-term agreement signed with Saudi Aramco. The contract is for 17 jackets – the steel frames supporting the processing platform – for the Berri and Marjan oilfields in the Arabian Gulf. Of the 17 platforms to be built and lifted into place, will be for the Berri and 8 for the Marjan fields.

    Under the six-year LTA, contractors will be responsible for delivering a number of offshore oil and gas producing platforms, tie-in platforms, pipelines, power cables, and all the related facilities, as required under the current master plan for Saudi Aramco's offshore fields.

    Due to their compact terminations, lighter weight and easier handling characteristics as compared to hand spliced cable laid slings, the customer selected the KimLock® resin terminated cable laid sling as their preferred choice for this project.

    SCOPE OF SUPPLY:

    4x KimLock® cable laid resin terminated sling; 7.91” (201mm) dia; CSBL 1,671MT; nominal length 95ft (28.9m).
    8x KimLock® cable laid resin terminated sling; 7.91” (201mm) dia; CSBL 1,671MT; nominal length 100ft (30.5m).
    8x KimLock® cable laid resin terminated sling; 7.91” (201mm) dia; CSBL 1,671MT; nominal length 105ft (32.0m).
    2x KimLock® cable laid resin terminated sling; 8.90” (226mm) dia; CSBL 2,022MT; nominal length 100ft (30.5m).

    All slings manufactured according to the new IMCA M179 Revision 1 Guidance Note.
    Manufactured and tested at KTL Offshore (Middle East) FZC and witnessed by ABS.

    Download PDF
  • Joint Development Area (JDA) Block B-17 Field Development Project: Multiple Jacket Lifts
    October 2017

    BACKGROUND


    In October 2017 KTL Offshore was awarded the  contract to design,manufacture and test 35 heavy lift slings for the jacket lifting phase of the JDA Block 17 project in the Gulf of Thailand.Due to their compact terminations, lighter weight and easier handling characteristics as compared to hand spliced cable laid slings,the customer selected the KimLock resin terminated cable laid sling as their preferred choice for this project.The Joint Development Area (JDA) Blocks B-17 & C-19 and B-17-01 Integrated Development Project involves the phased development of gas and condensate fields in blocks covering a 4,700km² area south of the Gulf of Thailand off the coast of Thailand and Malaysia.The water depths range between 55m and 65m.These blocks contain a total of 18 gas fields.

    SCOPE OF SUPPLY:

    KimLock® cable laid resin terminated sling; 238mm dia; CSBL 2,477
    MT; nominal length 20.00 m; x2 lengths.


    KimLock® cable laid resin terminated sling; 238mm dia; CSBL 2,477
    MT; nominal length 19.90 m; x1 length.


    KimLock® cable laid resin terminated sling; 238mm dia; CSBL 2,477
    MT; nominal length 19.80 m; x1 length.


    KimLock® cable laid resin terminated sling; 238mm dia; CSBL 2,477
    MT; nominal length 19.60 m; x2 lengths.


    KimLock® cable laid resin terminated sling; 238mm dia; CSBL 2,477
    MT; nominal length 19.50 m; x3 lengths.


    KimLock® cable laid resin terminated sling; 238mm dia; CSBL 2,477
    MT; nominal length 19.40 m; x1 length.


    KimLock® cable laid resin terminated sling; 238mm dia; CSBL 2,477
    MT; nominal length 19.20 m; x2 lengths.


    KimLock® cable laid resin terminated sling; 168mm dia; CSBL 1,254
    MT; nominal length 46.00 m; x4 lengths.


    KimLock® cable laid resin terminated sling; 168mm dia; CSBL 1.254
    MT; nominal length 50.00 m; x6 lengths.


    KimLock® cable laid resin terminated sling; 132mm dia; CSBL 827
    MT; nominal length 70.60 m; x3 lengths.


    KimLock® cable laid resin terminated sling; 132mm dia; CSBL 827
    MT; nominal length 46.00 m; x4 lengths.


    KimLock® cable laid resin terminated sling; 132mm dia; CSBL 827
    MT; nominal length 40.00 m; x6 lengths.

    Download PDF
  • Karan Project : Multiple Platform Lifts
    August 2017

    BACKGROUND


    In 2017 KTL Offshore was awarded the contract to design,manufacture and test 30 heavy lift slings and grommets for the KARAN project in the Kingdom of Saudi Arabia.The slings were tested on our KT1000 horizontal test bed to ensure the critical length tolerances were achieved – one of the largest test facilities in the Middle East. The EPCI contract was awarded by Saudi Aramco, which involved the engineering, procurement, transportation and installation of offshore structures including observation platform, wellhead production deck module, auxiliary platforms, 20" internally cladded flow line and composite power cable.The Karan gas field is located offshore of the Arabian Gulf in water depths of 40m to 60m. It is the first non-associated gas field being developed in the Kingdom of Saudi Arabia.The field is owned and operated by Saudi Aramco, a state-owned oil and gas company.

    SCOPE OF SUPPLY:
    Cable Laid Grommets:
    • Dia: 228mm; length: 20.86 meters; CGBL: 4,794 MT; x2 lengths.
    • Dia: 213mm; length: 21.36 meters; CGBL: 4,061 MT; x2 lengths.
    • Dia: 213mm; length: 32.18 meters; CGBL: 3,672 MT; x2 lengths.
    • Dia: 192mm; length: 31.70 meters; CGBL: 3,384 MT; x2 lengths.
    • Dia: 162mm; length: 37.94 meters; CGBL: 2,481 MT; x2 lengths.
    • Dia: 114mm; length: 31.00 meters; CGBL: 1,156 MT; x4 lengths.
    Cable Laid Slings (Hand Spliced):
    • Dia: 225mm; length: 48.37 meters; CSBL: 1,691 MT; x2 lengths.
    • Dia: 204mm; length: 48.36 meters; CSBL: 1,418 MT; x2 lengths.
    • Dia: 204mm; length: 43.00 meters; CSBL: 1,418 MT; x2 lengths.
    • Dia: 191mm; length: 42.41 meters; CSBL: 1,278 MT; x2 lengths.
    • Dia: 176mm; length: 50.10 meters; CSBL: 1,094 MT; x2 lengths.
    • Dia: 152mm; length: 40.00 meters; CSBL: 816 MT; x2 lengths.
    • Dia: 150mm; length: 31.00 meters; CSBL: 805 MT; x2 lengths.
    • Dia: 128mm; length: 42.50 meters; CSBL: 585 MT; x2 lengths.
    Manufactured and tested at KTL Offshore (Middle East) FZC and
    witnessed by BV.

    Download PDF
  • Shah Deniz Full Field Development (FFD) Project Stage 2
    February 2017

    KimLift™ Synthetic Slings – Deep Water

    Installation

    DATE

    February 2017

    BACKGROUND

    KTL Offshore was awarded the scope of supply for 12x KimLift™ synthetic heavy lift slings to be used for the installation of deep water jackets in the Caspian Sea. The KimLift™ slings were selected due to their light weight, high strength and extreme durability and unparalleled successful track record in the heavy lift industry. The KimLift™ slings are made using HMPE synthetic material, having the same strength as the equivalent sized steel wire rope sling. When used subsea the slings have neutral buoyancy increasing hook payload as well as operational efficiency. Using our Engineered Length Control™ technology the slings were produced to 0.25% length tolerance (under load).

    The Shah Deniz field is located 90 kilometres offshore Azerbaijan in water depths of up to 550 meters. The Full Field Development project undertaken by BP is one of the largest gas development projects in the world.

     

    SCOPE OF SUPPLY:

    6x KimLift™ synthetic round slings; MBL 1,447 metric tons; 128mm; nominal length16.4 meters.

    6x KimLift™ synthetic round slings; MBL 1,447 metric tons; 128mm; nominal length16.5 meters.

    Manufactured and tested by KTL Offshore Pte Ltd (Singapore). Tested and certified by ABS at KTL Offshore (Malaysia) Sdn Bhd.

    Download PDF
  • Trat Field Development
    January 2017

    BACKGROUND

    KTL Offshore was awarded the scope of supply for the heavy lift slings and grommets to be used for the installation of multiple new wellhead platforms

    and subsea pipelines for Chevron in the Trat Field in the Gulf of Thailand.

    This project showcases spectacularly the wide range of heavy lift options KTL Offshore can offer: cable laid grommets, resin terminated cable laid

    slings as well as braided slings. Each option caters

    to a specific requirement from the customer

     

    SCOPE OF SUPPLY:

    1x KimLock™resin terminated steel wire rope cable laid sling; diameter 242mm; CSBL 2,982 MT and nominal length 12.00 meters.

    2x KimFlex™ braided steel wire rope slings ; diameter 224mm; CSBL 1,699MT and nominal length 15.50 meters.

    2x KimFlex™ braided steel wire rope slings ; diameter 224mm; CSBL 1,699MT and nominal length 17.0 meters.

    4x Cable laid steel wire rope grommets; diameter 114mm; CGBL 1,275 MT and nominal length 7.50 meters.

    Manufactured and tested by KTL Offshore (Malaysia) Sdn Bhd. Witnessed and certified by ABS.

    Download PDF
  • NASR Full Field Development Project: Multiple Jacket Lifts
    January 2017

    BACKGROUND
    In November 2016 KTL Offshore was awarded the contract to design, manufacture and test 22 heavy lift slings for the jacket lifting phase of the NASR project in Abu Dhabi. Due to their compact terminations, lighter weight and easier handling characteristics as compared to hand spliced cable laid slings, the customer selected the KimLock™ resin terminated cable laid sling as their preferred choice for this project.

    The full scope of the NASR project includes engineering, procurement, construction, installation and commissioning work for the super complex comprising  a  gas  treatment  platform,  a  separation  platform,  an accommodation platform; laying 144 km subsea power and 55 km infield cables; and modifying an existing manifold tower and two wellhead towers.

    Upon completion by the second half of 2019, the facilities will increase the daily oil production capacity of the offshore field to 65,000 barrels from the current 22,000 barrels.

    The NASR oil field is situated130 km northwest of Abu Dhabi, UAE.

    Download PDF